A few years ago, the hard part of a data center project was finding the right site. Today, the question a project lives or dies on is when it can get energized. The industry calls this time to power, and it now shapes where, when, and whether new data centers get built.
Power isn’t a single problem. It’s a chain of dependencies, and a delay at any one link holds up everything behind it. That chain maps almost exactly onto the people a developer needs to hire, which is why I think time to power is as much a talent question as an infrastructure one.
Land is only the starting point
Securing a site used to feel like the finish line for early-stage development. Now it’s much closer to the starting line. In parts of the country the grid has no spare capacity to serve a new large load. In the conversations I’m having, states and utilities have become far more cautious about which projects they allow to connect, and some are pushing back on new data centers altogether until the power question is answered.
That changes the critical path. Developers now have to ask where they can get energized and how soon, not just where they can build. They also have to ask it much earlier in the process than they used to.
The four links in the power chain
When I talk about power, I mean everything from the utility’s generating capacity down to the equipment sitting on site. It helps to think of it as four connected links.
Utility capacity. On the utility side, there often isn’t enough power to go around for every data center that wants it. Utilities have to forecast load growth years in advance, and a wave of large, fast-moving data center requests is hard to plan for. Wood Mackenzie expects US data center capacity to climb from around 24 GW in mid-2026 to 110 GW by 2030, according to Reuters.
Interconnection. Even when new generation is being built, connecting it to the grid takes time. Berkeley Lab’s Queued Up 2026 analysis found that, in the regions with available data, the median wait from interconnection request to commercial operation was more than five years for power projects completed in 2025. Any new grid-connected plant built to serve data center demand has to go through that same process.
Substations and transformers. Then there’s the electrical infrastructure itself. New substations need to be built, and the transformers and switchgear that go into them are in short supply. According to Wood Mackenzie, generator step-up transformer lead times passed 160 weeks in early 2026, and high-voltage circuit breakers reached 125 weeks in the second half of 2025. One California utility now buys large substation transformers for projects it expects five years out.
On-site generation. Increasingly, data centers are expected to bring their own power. Some of the developers I speak to are being told by the state that they need their own generation, and grid operators are moving in a similar direction. PJM, which runs the grid across much of the Mid-Atlantic and Midwest, has asked federal regulators to approve a rule requiring new large-load customers to bring their own supply onto the grid. Where a project has to build its own generation, a data center developer becomes something closer to a power developer, with all the permitting, engineering, and fuel-supply questions that come with it.
Why time to power is a people problem
What stands out to me about that chain is that every link depends on a different set of specialists. Securing capacity needs people who understand utility relationships and load forecasting. Interconnection needs engineers and project managers who have already been through the study process in that region.
Substation and transformer work calls for electrical engineers and procurement leads who know how to secure equipment slots years in advance, and our power infrastructure equipment team in New York sees a lot of that demand. On-site generation needs power development, permitting, and engineering experience that many data center teams have never had to hold in-house.
At Storm4, our teams work across almost every one of those areas, from power trading and grid management to critical power and data center hiring. That gives me a clear view of how closely these markets are now tied together. A delay in one of them tends to show up as hiring pressure in another.
That’s why power expertise belongs at the planning stage rather than being treated as a construction problem. By the time a project breaks ground, most of the decisions that set its energization date have already been made.
Five questions to answer before you commit to a site
If you’re planning a new facility, these are the questions I’d want your team to be able to answer early:
- Has the utility confirmed it can serve the full load, and on what timeline?
- Who owns interconnection on your team, and have they been through the process in this region before?
- Are long-lead items such as transformers and switchgear already on order, or will procurement only start once design is complete?
- If on-site generation is needed, who on the team has the power development experience to lead it?
- Does the team understand the state’s current rules on large loads and self-generation?
If the honest answer to any of these is that you’ll hire for it later, that’s usually where the schedule risk is hiding.